Installation tasks
When the SambaNova DataScale SN30 rack is rolled to its location on the datacenter floor, perform the following tasks in sequence.
| If requested, SambaNova can handle the hardware installation tasks. |
| Task | Description | Notes |
|---|---|---|
1 |
Ensure that you’ve performed all site preparation tasks |
|
2 |
Inspect the rack for any damage that might have resulted from local handling or relocation within the customer facility. |
Contact SambaNova customer support if you see any problems. |
3 |
Leave the system on the datacenter floor for 24 hours under ambient environmental conditions before powering on the rack. |
Allows the components to acclimatize to the environment, prevents the effects of sudden cooling or heating, and removes the possibility of any condensation accumulation. |
4 |
Attach the rack’s bus grounding bar to the facility’s ground. |
|
5 |
Permanently attach the rack to the datacenter floor in its intended location using the tie-down brackets and bolts. |
Consult your facilities staff about preparing the tie-down bolt holes and locations. Lower the rack feet in each corner of the rack, if it’s standard procedure at your site. |
6 |
Connect the datacenter network cable drop to the Juniper high-bandwidth data switch to ports 27-30 for LAG (see Network infrastructure requirements). |
You can use a single LAG port. Ensure that the switch that is connecting to this Juniper high-bandwidth data switch is configured for a LAG. If a LAG configured port is not available from the customer switch, use port 31 on the Juniper high-bandwidth data switch. |
7 |
Connect the second datacenter access network cable drop to the dongle on the left-rear vertical bar of the rack for the Lantronix serial console server management interface port |
|
8 |
Connect the four power plugs from the PDUs to the four 3-phase power sockets |
|
9 |
Observe the rack during power-on to make sure there are no issues with the PDUs or other rack components. Determine whether any warning LEDs on the rack components are lit. |
If warning or error lights appear, see the support knowledge base articles at https://support.sambanova.ai. NOTE: In a single-node DataScale deployment, an amber light appears on port 16 of the QFX5130. This is expected behavior for this switch. |